{"id":100613,"date":"2026-10-17T12:55:33","date_gmt":"2026-10-17T12:55:33","guid":{"rendered":"https:\/\/skyplanner.ai\/?p=100613"},"modified":"2026-10-17T12:56:19","modified_gmt":"2026-10-17T12:56:19","slug":"matrice-dei-tempi-di-setup","status":"publish","type":"post","link":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/","title":{"rendered":"Matrice dei tempi di setup: come creare e leggere i dati"},"content":{"rendered":"<div class=\"gb-container gb-container-article01 article-main-content-container\">\n\n<h1 class=\"wp-block-heading\">Matrice dei tempi di setup: come creare e leggere i dati<\/h1>\n\n<div class=\"gb-container gb-container-article02\">\n\n<p><a href=\"\/it\/\">Home<\/a> &raquo; <a href=\"https:\/\/skyplanner.ai\/it\/risorse\/\">Risorse<\/a> &raquo; Matrice dei tempi di setup: come creare e leggere i dati<\/p>\n\n\n<p class=\"yoast-reading-time__wrapper\"><span class=\"yoast-reading-time__icon\"><svg aria-hidden=\"true\" focusable=\"false\" data-icon=\"clock\" width=\"20\" height=\"20\" fill=\"none\" stroke=\"currentColor\" style=\"display:inline-block;vertical-align:-0.1em\" role=\"img\" xmlns=\"http:\/\/www.w3.org\/2000\/svg\" viewBox=\"0 0 24 24\"><path stroke-linecap=\"round\" stroke-linejoin=\"round\" stroke-width=\"2\" d=\"M12 8v4l3 3m6-3a9 9 0 11-18 0 9 9 0 0118 0z\"><\/path><\/svg><\/span><span class=\"yoast-reading-time__spacer\" style=\"display:inline-block;width:1em\"><\/span><span class=\"yoast-reading-time__descriptive-text\">Tempo di lettura stimato: <\/span><span class=\"yoast-reading-time__reading-time\">8<\/span><span class=\"yoast-reading-time__time-unit\"> minuti<\/span><\/p>\n\n<\/div>\n<div class=\"gb-container gb-container-article03\">\n\n<p>Una matrice dei tempi di setup \u00e8 una tabella che indica quanto tempo serve a una macchina per passare da un prodotto o da un assetto di attrezzaggio a un altro. Ogni cella risponde a una domanda precisa: se ora la macchina \u00e8 attrezzata per questo prodotto, quanto tempo occorrer\u00e0 prima di poter produrre il successivo?<\/p>\n\n\n<p>Il senso del passaggio conta. Per passare da un colore chiaro a uno scuro pu\u00f2 bastare un breve lavaggio, mentre per tornare al colore chiaro occorre una pulizia molto pi\u00f9 lunga. Un unico tempo medio di attrezzaggio nasconde questa differenza. Il piano pu\u00f2 quindi riservare troppo poco tempo a un cambio complesso e troppo a uno semplice.<\/p>\n\n\n<p>Una matrice utile mette in evidenza queste differenze prima che compromettano il piano. Aiuta anche a individuare le caratteristiche di prodotto in base alle quali conviene raggruppare le operazioni in SkyPlanner. In questo modo puoi ridurre i cambi non necessari senza ricostruire manualmente le code delle macchine ogni volta che cambiano le priorit\u00e0.<\/p>\n\n\n<h2 class=\"wp-block-heading\">Come leggere una matrice dei tempi di setup<\/h2>\n\n\n<p>La riga indica l&#8217;assetto di partenza, la colonna quello di destinazione. Mantieni queste indicazioni nella tabella, anche se al momento tutti sanno come leggerla. Invertirle significa pianificare sulla base di un presupposto errato.<\/p>\n\n\n<p>Immagina una macchina di verniciatura che lavori con tre famiglie di colori. I tempi seguenti sono puramente illustrativi: non sono risultati di clienti n\u00e9 standard di pulizia consigliati.<\/p>\n\n\n<figure class=\"wp-block-table\"><table><thead><tr><th>Da famiglia attuale \/ A famiglia successiva<\/th><th>A: chiaro<\/th><th>B: medio<\/th><th>C: scuro<\/th><\/tr><\/thead><tbody><tr><td>A: chiaro<\/td><td>0 min<\/td><td>12 min<\/td><td>18 min<\/td><\/tr><tr><td>B: medio<\/td><td>35 min<\/td><td>0 min<\/td><td>10 min<\/td><\/tr><tr><td>C: scuro<\/td><td>50 min<\/td><td>28 min<\/td><td>0 min<\/td><\/tr><\/tbody><\/table><\/figure>\n\n\n<p>Per passare dal chiaro allo scuro, cerca l&#8217;incrocio tra la riga A e la colonna C: 18 minuti. Per passare dallo scuro al chiaro, cerca la riga C e la colonna A: 50 minuti. Sono due passaggi distinti, non due modi di leggere lo stesso valore.<\/p>\n\n\n<p>La diagonale rappresenta la prosecuzione del lavoro all&#8217;interno della stessa famiglia. Qui i valori sono pari a zero perch\u00e9 l&#8217;esempio presuppone che tra quelle operazioni non serva alcun attrezzaggio. Non applicare automaticamente questa ipotesi alla tua matrice. Anche all&#8217;interno di una famiglia potrebbero essere necessari un cambio dell&#8217;attrezzatura di fissaggio, un controllo per il rilascio del lotto o un&#8217;altra attivit\u00e0 preparatoria.<\/p>\n\n\n<p>La tabella diventa utile quando tieni conto delle condizioni iniziali della macchina. Supponiamo che sia attualmente predisposta per lo scuro e che le prossime operazioni prevedano prima il chiaro e poi il medio. Il tempo da riservare all&#8217;attrezzaggio \u00e8:<\/p>\n\n\n<ul class=\"wp-block-list\"><li>Da scuro a chiaro: 50 minuti.<\/li><li>Da chiaro a medio: 12 minuti.<\/li><li>Tempo totale di cambio produzione: 62 minuti, a cui aggiungere i tempi di lavorazione delle operazioni.<\/li><\/ul>\n\n\n<p>Considerando solo il passaggio tra le due nuove operazioni, riserveresti 12 minuti, trascurando i 50 minuti del cambio iniziale. La prima operazione del piano non inizia necessariamente su una macchina pulita e priva di un assetto precedente.<\/p>\n\n\n<h2 class=\"wp-block-heading\">Come costruire una matrice dei tempi di setup affidabile<\/h2>\n\n\n<p>Parti da una risorsa produttiva per la quale le ipotesi sui tempi di attrezzaggio incidono davvero sulle decisioni di consegna. Una matrice circoscritta, con dati di cui puoi verificare l&#8217;origine, \u00e8 pi\u00f9 utile di una griglia che copre l&#8217;intero stabilimento ma \u00e8 piena di congetture.<\/p>\n\n\n<h3 class=\"wp-block-heading\">Definisci la macchina e gli assetti di attrezzaggio<\/h3>\n\n\n<p>Specifica a quale macchina o linea si riferisce la matrice. Il passaggio tra gli stessi due prodotti pu\u00f2 richiedere tempi diversi su impianti diversi: non trasferire quindi un valore da una macchina all&#8217;altra senza verificarlo.<\/p>\n\n\n<p>Individua poi ci\u00f2 che determina il cambio: utensili, grado del materiale, colore, dimensioni, attrezzatura di fissaggio o un&#8217;altra caratteristica produttiva. Usa i codici prodotto quando i singoli prodotti comportano cambi diversi. Ricorri a famiglie di attrezzaggio quando i prodotti hanno effettivamente le stesse esigenze di cambio produzione.<\/p>\n\n\n<p>Una categoria commerciale non corrisponde necessariamente a una famiglia di attrezzaggio. Due prodotti simili a catalogo possono richiedere utensili diversi. Viceversa, pi\u00f9 prodotti realizzati per clienti specifici possono utilizzare le stesse impostazioni macchina. Raggruppali in base a ci\u00f2 che l&#8217;operatore deve effettivamente cambiare.<\/p>\n\n\n<h3 class=\"wp-block-heading\">Concorda quando inizia e quando finisce la misurazione<\/h3>\n\n\n<p>Scegli criteri uniformi per l&#8217;inizio e la fine della misurazione. Per valutare la capacit\u00e0 produttiva, una misura utile \u00e8 il tempo trascorso dall&#8217;ultimo pezzo conforme dell&#8217;operazione precedente al primo pezzo conforme di quella successiva. Specifica se il valore comprende pulizia, regolazioni, produzione di prova e approvazione del primo pezzo.<\/p>\n\n\n<p>Mantieni distinte le componenti del tempo quando influiscono sulla pianificazione. Se la macchina resta ferma in attesa di un addetto al controllo, quell&#8217;attesa ne riduce la disponibilit\u00e0, ma il problema non \u00e8 lo stesso di un cambio utensile lento. Registra la causa, anzich\u00e9 inglobare ogni ritardo in un unico tempo di attrezzaggio senza spiegarlo.<\/p>\n\n\n<p>Distingui anche il tempo di indisponibilit\u00e0 della macchina dal tempo di manodopera. Se due persone lavorano insieme durante una parte del cambio produzione, il tempo di indisponibilit\u00e0 della macchina non \u00e8 la somma dei minuti di lavoro di ciascuna.<\/p>\n\n\n<p>Quando configurerai i dati di schedulazione, verifica che questi criteri di misurazione siano coerenti con i tempi di attrezzaggio, disattrezzaggio o di altro tipo gi\u00e0 inclusi. La stessa attivit\u00e0 di pulizia non deve essere conteggiata due volte nel calcolo della capacit\u00e0 impegnata.<\/p>\n\n\n<h3 class=\"wp-block-heading\">Raccogli le rilevazioni con il contesto necessario<\/h3>\n\n\n<p>Per ogni cambio osservato, registra la risorsa produttiva, l&#8217;assetto precedente, quello successivo, il tempo trascorso, la data e tutte le circostanze che influiscono sul risultato. Conserva la rilevazione da cui deriva il valore della matrice, cos\u00ec da poterlo verificare in seguito.<\/p>\n\n\n<p>Pi\u00f9 rilevazioni permettono di capire se un passaggio ha tempi abbastanza stabili o dipende da un&#8217;altra condizione. Se cambi simili presentano variazioni notevoli, cercane la causa prima di ridurli a una media. Attrezzature di fissaggio diverse, preparazione mancante o ritardi ricorrenti nelle approvazioni possono richiedere interventi diversi.<\/p>\n\n\n<p>Scegli un tempo da riservare nel piano che sia rappresentativo delle condizioni previste e documenta il criterio adottato. Un guasto isolato non deve diventare, senza spiegazioni, parte del normale tempo di cambio produzione; un ritardo ricorrente non deve sparire solo perch\u00e9 \u00e8 scomodo.<\/p>\n\n\n<h3 class=\"wp-block-heading\">Distingui stime, dati sconosciuti e passaggi vietati<\/h3>\n\n\n<p>Una cella senza misurazioni non indica un cambio da zero minuti. Contrassegnala come dato sconosciuto oppure come stima, specificando su cosa si basa e chi \u00e8 responsabile della verifica. Inizia convalidando i passaggi che saranno probabilmente necessari per gli ordini attualmente in portafoglio, soprattutto quelli in cui un errore metterebbe a rischio una consegna.<\/p>\n\n\n<p>Un passaggio vietato \u00e8 un caso ancora diverso. Richiede un vincolo di produzione esplicito, non una cella vuota o una durata enorme inventata. La matrice registra le conseguenze delle regole di processo sulla pianificazione; non stabilisce se un cambio sia accettabile dal punto di vista tecnico o della sicurezza.<\/p>\n\n\n<p>Verifica i valori delle famiglie alla luce delle eccezioni note. Se un prodotto richiede una pulizia aggiuntiva o un&#8217;ulteriore regolazione degli utensili, mantieni visibile questa differenza invece di farla scomparire nella media della famiglia.<\/p>\n\n\n<h2 class=\"wp-block-heading\">Cosa dovrebbe cambiare nel piano di produzione grazie alla matrice<\/h2>\n\n\n<p>Cerca gli andamenti ricorrenti, non solo la cella con il valore pi\u00f9 basso. Una colonna con tempi elevati indica un assetto che richiede molto tempo per essere raggiunto. Una riga con tempi elevati indica un assetto da cui \u00e8 oneroso uscire. Una grande differenza tra i due sensi di passaggio segnala che la sequenza delle lavorazioni merita attenzione.<\/p>\n\n\n<p>Questi andamenti aiutano a porsi domande pi\u00f9 mirate. Si possono eseguire consecutivamente operazioni compatibili? Si pu\u00f2 evitare un ritorno oneroso a un attrezzaggio precedente? Un raggruppamento per famiglia apparentemente conveniente nasconde un&#8217;eccezione importante? Per quale passaggio frequente vale la pena migliorare le attivit\u00e0 concrete di cambio produzione?<\/p>\n\n\n<p>Quest&#8217;ultima domanda rientra nell&#8217;ambito dello <a href=\"https:\/\/skyplanner.ai\/it\/risorse\/tempi-di-setup\/\">SMED<\/a>: ridurre il lavoro e il tempo necessari per il cambio stesso. La matrice ha un ruolo diverso. Descrive i passaggi di cui la schedulazione deve tenere conto e va aggiornata quando migliora il metodo operativo.<\/p>\n\n\n<p>Un tempo totale di attrezzaggio ridotto non basta comunque a definire un piano di produzione completo. Per l&#8217;operazione successiva servono anche materiale, una risorsa produttiva idonea e il completamento delle operazioni precedenti. La priorit\u00e0 di consegna pu\u00f2 giustificare l&#8217;interruzione di un raggruppamento conveniente. Confronta l&#8217;andamento dei tempi di attrezzaggio con questi requisiti, anzich\u00e9 riordinare la coda al solo scopo di ottenere il cambio pi\u00f9 breve.<\/p>\n\n\n<h2 class=\"wp-block-heading\">Dai dati di attrezzaggio a un piano sempre aggiornato con SkyPlanner<\/h2>\n\n\n<p>Il passo successivo, sul piano pratico, \u00e8 integrare ipotesi attendibili sui tempi di attrezzaggio nel processo di schedulazione, non mantenere una matrice separata e correggere manualmente il piano in parallelo. SkyPlanner APS riunisce informazioni di attrezzaggio, capacit\u00e0 delle risorse produttive, dipendenze tra operazioni e priorit\u00e0 di consegna in un unico <a href=\"https:\/\/skyplanner.ai\/it\/risorse\/cos-e-la-schedulazione-della-produzione\/\">piano di produzione<\/a>.<\/p>\n\n\n<p>Nei centri di lavoro in cui la compatibilit\u00e0 tra le propriet\u00e0 dei prodotti permette di ridurre i cambi, il raggruppamento per propriet\u00e0 di SkyPlanner \u00e8 un modo diretto per mettere a frutto ci\u00f2 che hai rilevato. Ai prodotti sono associate propriet\u00e0 e relativi valori, come la famiglia di utensili o il grado del materiale. Un centro di lavoro pu\u00f2 usare la propriet\u00e0 pertinente per raggruppare ordini di lavoro simili.<\/p>\n\n\n<p>La regola \u00abConsenti similitudine\u00bb del centro di lavoro prevede un tempo di attrezzaggio per operazioni diverse e la scelta della propriet\u00e0 da considerare. Nelle Priorit\u00e0 dinamiche imposti anche l&#8217;importanza di eseguire in successione operazioni simili. Il calcolo della schedulazione ha cos\u00ec un criterio per mantenere consecutive le operazioni compatibili, pur tenendo conto delle altre priorit\u00e0 che hai scelto.<\/p>\n\n\n<p>Per esempio, se le rilevazioni mostrano che pi\u00f9 codici articolo usano gli stessi utensili e che i cambi avvengono soprattutto tra famiglie di utensili, questa propriet\u00e0 \u00e8 pi\u00f9 utile di un raggruppamento per cliente o nome del prodotto. Trasformi cos\u00ec l&#8217;esperienza del reparto in una regola di schedulazione ripetibile, anzich\u00e9 affidarti alla memoria del pianificatore per ogni combinazione compatibile.<\/p>\n\n\n<p>Una matrice che distingue i due sensi di passaggio pu\u00f2 anche far emergere esigenze pi\u00f9 complesse. I passaggi da 18 e 50 minuti dell&#8217;esempio di verniciatura non possono essere rappresentati fedelmente da un unico tempo comune per operazioni diverse. Se queste differenze specifiche tra coppie di prodotti sono determinanti nella tua produzione, porta a una demo di SkyPlanner i dati di entrambi i sensi e le eventuali eccezioni, cos\u00ec da verificare il modello di attrezzaggio rispetto al tuo processo reale.<\/p>\n\n\n<p>Arcturus, l&#8217;intelligenza artificiale di SkyPlanner per la schedulazione, calcola la sequenza delle lavorazioni in base alle regole e alle priorit\u00e0 configurate, e il diagramma di Gantt ne mostra il risultato. Con la rischedulazione automatica abilitata, variazioni rilevanti agli ordini, alle operazioni completate o alla capacit\u00e0 possono attivare un ricalcolo. Dedichi meno tempo a ricostruire le code e pi\u00f9 tempo a decidere quali impegni di consegna richiedono attenzione.<\/p>\n\n\n<h2 class=\"wp-block-heading\">Parti dai cambi produzione necessari per i prossimi ordini<\/h2>\n\n\n<p>Per fare progressi non serve misurare i tempi di passaggio tra tutte le possibili coppie di prodotti. Parti da una macchina importante, dal suo attrezzaggio attuale e dai passaggi previsti nel prossimo piano di produzione. Verifica i passaggi in senso inverso che richiedono pi\u00f9 tempo e le celle che contengono ancora valori stimati. \u00c8 spesso l\u00ec che si perde il margine di un piano che sembrava averne a sufficienza.<\/p>\n\n\n<p>Poi metti a frutto questi dati. <a href=\"https:\/\/skyplanner.ai\/it\/contatto-vendite\/\">Prenota una demo di SkyPlanner<\/a> portando le tue famiglie di attrezzaggio, i tempi misurati per alcuni passaggi e un insieme rappresentativo di ordini reali. Potrai valutare come combinare raggruppamenti, tempi previsti per l\u2019attrezzaggio e priorit\u00e0 di consegna nella tua produzione. Se preferisci prima esplorare l\u2019ambiente di schedulazione, <a href=\"https:\/\/skyplanner.ai\/it\/prova\/\">prova SkyPlanner con dati dimostrativi<\/a>.<\/p>\n\n<\/div>\n<\/div>","protected":false},"excerpt":{"rendered":"<p>Matrice dei tempi di setup: come creare e leggere i dati Home &raquo; Risorse &raquo; Matrice dei tempi di setup: come creare e leggere i dati Una matrice dei tempi di setup \u00e8 una tabella che indica quanto tempo serve a una macchina per passare da un prodotto o da un assetto di attrezzaggio a &#8230; <a title=\"Matrice dei tempi di setup: come creare e leggere i dati\" class=\"read-more\" href=\"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/\" aria-label=\"Per saperne di pi\u00f9 su Matrice dei tempi di setup: come creare e leggere i dati\">Leggi tutto<\/a><\/p>\n","protected":false},"author":3,"featured_media":100639,"comment_status":"closed","ping_status":"closed","sticky":false,"template":"","format":"standard","meta":{"_acf_changed":false,"inline_featured_image":false,"_uag_custom_page_level_css":"","footnotes":""},"categories":[2556,316],"tags":[],"class_list":["post-100613","post","type-post","status-publish","format-standard","has-post-thumbnail","hentry","category-efficienza-produttiva","category-risorse","generate-columns","tablet-grid-50","mobile-grid-100","grid-parent","grid-33"],"acf":[],"yoast_head":"<!-- This site is optimized with the Yoast SEO Premium plugin v28.3 (Yoast SEO v28.7) - https:\/\/yoast.com\/product\/yoast-seo-premium-wordpress\/ -->\n<title>Matrice dei tempi di setup: come creare e leggere i dati<\/title>\n<meta name=\"description\" content=\"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.\" \/>\n<meta name=\"robots\" content=\"index, follow, max-snippet:-1, max-image-preview:large, max-video-preview:-1\" \/>\n<link rel=\"canonical\" href=\"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/\" \/>\n<meta property=\"og:locale\" content=\"it_IT\" \/>\n<meta property=\"og:type\" content=\"article\" \/>\n<meta property=\"og:title\" content=\"Matrice dei tempi di setup: come creare e leggere i dati\" \/>\n<meta property=\"og:description\" content=\"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.\" \/>\n<meta property=\"og:url\" content=\"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/\" \/>\n<meta property=\"og:site_name\" content=\"SkyPlanner\" \/>\n<meta property=\"article:published_time\" content=\"2026-10-17T12:55:33+00:00\" \/>\n<meta property=\"article:modified_time\" content=\"2026-10-17T12:56:19+00:00\" \/>\n<meta property=\"og:image\" content=\"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png\" \/>\n\t<meta property=\"og:image:width\" content=\"1672\" \/>\n\t<meta property=\"og:image:height\" content=\"941\" \/>\n\t<meta property=\"og:image:type\" content=\"image\/png\" \/>\n<meta name=\"author\" content=\"Jussi M\u00e4ntyl\u00e4\" \/>\n<meta name=\"twitter:card\" content=\"summary_large_image\" \/>\n<meta name=\"twitter:label1\" content=\"Scritto da\" \/>\n\t<meta name=\"twitter:data1\" content=\"Jussi M\u00e4ntyl\u00e4\" \/>\n\t<meta name=\"twitter:label2\" content=\"Tempo di lettura stimato\" \/>\n\t<meta name=\"twitter:data2\" content=\"9 minuti\" \/>\n<script type=\"application\/ld+json\" class=\"yoast-schema-graph\">{\"@context\":\"https:\\\/\\\/schema.org\",\"@graph\":[{\"@type\":\"Article\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#article\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/\"},\"author\":{\"name\":\"Jussi M\u00e4ntyl\u00e4\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#\\\/schema\\\/person\\\/d90eac23cfbf5af3a2c4a38ff10376b5\"},\"headline\":\"Matrice dei tempi di setup: come creare e leggere i dati\",\"datePublished\":\"2026-10-17T12:55:33+00:00\",\"dateModified\":\"2026-10-17T12:56:19+00:00\",\"mainEntityOfPage\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/\"},\"wordCount\":1937,\"publisher\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#organization\"},\"image\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2026\\\/10\\\/changeover-matrix-hero.png\",\"articleSection\":[\"Efficienza produttiva\",\"risorse\"],\"inLanguage\":\"it-IT\"},{\"@type\":\"WebPage\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/\",\"name\":\"Matrice dei tempi di setup: come creare e leggere i dati\",\"isPartOf\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#website\"},\"primaryImageOfPage\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#primaryimage\"},\"image\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#primaryimage\"},\"thumbnailUrl\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2026\\\/10\\\/changeover-matrix-hero.png\",\"datePublished\":\"2026-10-17T12:55:33+00:00\",\"dateModified\":\"2026-10-17T12:56:19+00:00\",\"description\":\"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.\",\"breadcrumb\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#breadcrumb\"},\"inLanguage\":\"it-IT\",\"potentialAction\":[{\"@type\":\"ReadAction\",\"target\":[\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/\"]}]},{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#primaryimage\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2026\\\/10\\\/changeover-matrix-hero.png\",\"contentUrl\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2026\\\/10\\\/changeover-matrix-hero.png\",\"width\":1672,\"height\":941,\"caption\":\"Light and dark coating swatches with spray and brush-cleaning symbols for product changeovers.\"},{\"@type\":\"BreadcrumbList\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/risorse\\\/matrice-dei-tempi-di-setup\\\/#breadcrumb\",\"itemListElement\":[{\"@type\":\"ListItem\",\"position\":1,\"name\":\"Home\",\"item\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/\"},{\"@type\":\"ListItem\",\"position\":2,\"name\":\"Matrice dei tempi di setup: come creare e leggere i dati\"}]},{\"@type\":\"WebSite\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#website\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/\",\"name\":\"SkyPlanner\",\"description\":\"AI-powered production scheduling and planning software\",\"publisher\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#organization\"},\"potentialAction\":[{\"@type\":\"SearchAction\",\"target\":{\"@type\":\"EntryPoint\",\"urlTemplate\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/?s={search_term_string}\"},\"query-input\":{\"@type\":\"PropertyValueSpecification\",\"valueRequired\":true,\"valueName\":\"search_term_string\"}}],\"inLanguage\":\"it-IT\"},{\"@type\":\"Organization\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#organization\",\"name\":\"Skycode Oy\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/\",\"logo\":{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#\\\/schema\\\/logo\\\/image\\\/\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2022\\\/05\\\/Skyplanner-logo-2.svg\",\"contentUrl\":\"https:\\\/\\\/skyplanner.ai\\\/wp-content\\\/uploads\\\/2022\\\/05\\\/Skyplanner-logo-2.svg\",\"width\":223,\"height\":43,\"caption\":\"SkyPlanner APS\"},\"image\":{\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#\\\/schema\\\/logo\\\/image\\\/\"},\"legalName\":\"Skycode Oy\",\"alternateName\":[\"Skycode\",\"SkyPlanner\",\"SkyPlanner APS\"],\"description\":\"Skycode Oy is the Finnish software company that develops and publishes SkyPlanner APS, AI production scheduling and advanced planning and scheduling (APS) software for manufacturers worldwide. Founded in 1997 as a sole proprietorship and incorporated as Skycode Oy in 2008.\",\"foundingDate\":\"1997\",\"taxID\":\"2204947-0\",\"vatID\":\"FI22049470\",\"telephone\":\"+358407000002\",\"email\":\"support@skyplanner.ai\",\"address\":{\"@type\":\"PostalAddress\",\"streetAddress\":\"Rantakatu 2 G 11\",\"postalCode\":\"65100\",\"addressLocality\":\"Vaasa\",\"addressCountry\":\"FI\"},\"brand\":{\"@type\":\"Brand\",\"name\":\"SkyPlanner\"},\"knowsAbout\":[\"Production Scheduling\",\"Advanced Planning and Scheduling\",\"Manufacturing AI\",\"Finite Capacity Scheduling\",\"ERP Integration\",\"MES Integration\"],\"areaServed\":\"Worldwide\",\"contactPoint\":[{\"@type\":\"ContactPoint\",\"contactType\":\"sales\",\"url\":\"https:\\\/\\\/skyplanner.ai\\\/contact-sales\\\/\",\"areaServed\":\"Worldwide\"},{\"@type\":\"ContactPoint\",\"contactType\":\"customer support\",\"email\":\"support@skyplanner.ai\",\"telephone\":\"+358407000002\",\"areaServed\":\"Worldwide\"}],\"sameAs\":[\"https:\\\/\\\/www.wikidata.org\\\/wiki\\\/Q141672132\",\"https:\\\/\\\/skycode.fi\\\/\",\"https:\\\/\\\/www.linkedin.com\\\/company\\\/skycodeoy\\\/\",\"https:\\\/\\\/www.finder.fi\\\/IT-konsultointi+IT-palvelut\\\/Skycode+Oy\\\/Vaasa\\\/yhteystiedot\\\/1934882\"]},{\"@type\":\"Person\",\"@id\":\"https:\\\/\\\/skyplanner.ai\\\/it\\\/#\\\/schema\\\/person\\\/d90eac23cfbf5af3a2c4a38ff10376b5\",\"name\":\"Jussi M\u00e4ntyl\u00e4\",\"image\":{\"@type\":\"ImageObject\",\"inLanguage\":\"it-IT\",\"@id\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g\",\"url\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g\",\"contentUrl\":\"https:\\\/\\\/secure.gravatar.com\\\/avatar\\\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g\",\"caption\":\"Jussi M\u00e4ntyl\u00e4\"}}]}<\/script>\n<!-- \/ Yoast SEO Premium plugin. -->","yoast_head_json":{"title":"Matrice dei tempi di setup: come creare e leggere i dati","description":"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.","robots":{"index":"index","follow":"follow","max-snippet":"max-snippet:-1","max-image-preview":"max-image-preview:large","max-video-preview":"max-video-preview:-1"},"canonical":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/","og_locale":"it_IT","og_type":"article","og_title":"Matrice dei tempi di setup: come creare e leggere i dati","og_description":"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.","og_url":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/","og_site_name":"SkyPlanner","article_published_time":"2026-10-17T12:55:33+00:00","article_modified_time":"2026-10-17T12:56:19+00:00","og_image":[{"width":1672,"height":941,"url":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png","type":"image\/png"}],"author":"Jussi M\u00e4ntyl\u00e4","twitter_card":"summary_large_image","twitter_misc":{"Scritto da":"Jussi M\u00e4ntyl\u00e4","Tempo di lettura stimato":"9 minuti"},"schema":{"@context":"https:\/\/schema.org","@graph":[{"@type":"Article","@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#article","isPartOf":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/"},"author":{"name":"Jussi M\u00e4ntyl\u00e4","@id":"https:\/\/skyplanner.ai\/it\/#\/schema\/person\/d90eac23cfbf5af3a2c4a38ff10376b5"},"headline":"Matrice dei tempi di setup: come creare e leggere i dati","datePublished":"2026-10-17T12:55:33+00:00","dateModified":"2026-10-17T12:56:19+00:00","mainEntityOfPage":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/"},"wordCount":1937,"publisher":{"@id":"https:\/\/skyplanner.ai\/it\/#organization"},"image":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#primaryimage"},"thumbnailUrl":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png","articleSection":["Efficienza produttiva","risorse"],"inLanguage":"it-IT"},{"@type":"WebPage","@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/","url":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/","name":"Matrice dei tempi di setup: come creare e leggere i dati","isPartOf":{"@id":"https:\/\/skyplanner.ai\/it\/#website"},"primaryImageOfPage":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#primaryimage"},"image":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#primaryimage"},"thumbnailUrl":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png","datePublished":"2026-10-17T12:55:33+00:00","dateModified":"2026-10-17T12:56:19+00:00","description":"Una media pu\u00f2 nascondere cambi costosi. Crea una matrice dei tempi di setup, leggi i due sensi e usa dati migliori per pianificare con SkyPlanner.","breadcrumb":{"@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#breadcrumb"},"inLanguage":"it-IT","potentialAction":[{"@type":"ReadAction","target":["https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/"]}]},{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#primaryimage","url":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png","contentUrl":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png","width":1672,"height":941,"caption":"Light and dark coating swatches with spray and brush-cleaning symbols for product changeovers."},{"@type":"BreadcrumbList","@id":"https:\/\/skyplanner.ai\/it\/risorse\/matrice-dei-tempi-di-setup\/#breadcrumb","itemListElement":[{"@type":"ListItem","position":1,"name":"Home","item":"https:\/\/skyplanner.ai\/it\/"},{"@type":"ListItem","position":2,"name":"Matrice dei tempi di setup: come creare e leggere i dati"}]},{"@type":"WebSite","@id":"https:\/\/skyplanner.ai\/it\/#website","url":"https:\/\/skyplanner.ai\/it\/","name":"SkyPlanner","description":"AI-powered production scheduling and planning software","publisher":{"@id":"https:\/\/skyplanner.ai\/it\/#organization"},"potentialAction":[{"@type":"SearchAction","target":{"@type":"EntryPoint","urlTemplate":"https:\/\/skyplanner.ai\/it\/?s={search_term_string}"},"query-input":{"@type":"PropertyValueSpecification","valueRequired":true,"valueName":"search_term_string"}}],"inLanguage":"it-IT"},{"@type":"Organization","@id":"https:\/\/skyplanner.ai\/it\/#organization","name":"Skycode Oy","url":"https:\/\/skyplanner.ai\/it\/","logo":{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/skyplanner.ai\/it\/#\/schema\/logo\/image\/","url":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2022\/05\/Skyplanner-logo-2.svg","contentUrl":"https:\/\/skyplanner.ai\/wp-content\/uploads\/2022\/05\/Skyplanner-logo-2.svg","width":223,"height":43,"caption":"SkyPlanner APS"},"image":{"@id":"https:\/\/skyplanner.ai\/it\/#\/schema\/logo\/image\/"},"legalName":"Skycode Oy","alternateName":["Skycode","SkyPlanner","SkyPlanner APS"],"description":"Skycode Oy is the Finnish software company that develops and publishes SkyPlanner APS, AI production scheduling and advanced planning and scheduling (APS) software for manufacturers worldwide. Founded in 1997 as a sole proprietorship and incorporated as Skycode Oy in 2008.","foundingDate":"1997","taxID":"2204947-0","vatID":"FI22049470","telephone":"+358407000002","email":"support@skyplanner.ai","address":{"@type":"PostalAddress","streetAddress":"Rantakatu 2 G 11","postalCode":"65100","addressLocality":"Vaasa","addressCountry":"FI"},"brand":{"@type":"Brand","name":"SkyPlanner"},"knowsAbout":["Production Scheduling","Advanced Planning and Scheduling","Manufacturing AI","Finite Capacity Scheduling","ERP Integration","MES Integration"],"areaServed":"Worldwide","contactPoint":[{"@type":"ContactPoint","contactType":"sales","url":"https:\/\/skyplanner.ai\/contact-sales\/","areaServed":"Worldwide"},{"@type":"ContactPoint","contactType":"customer support","email":"support@skyplanner.ai","telephone":"+358407000002","areaServed":"Worldwide"}],"sameAs":["https:\/\/www.wikidata.org\/wiki\/Q141672132","https:\/\/skycode.fi\/","https:\/\/www.linkedin.com\/company\/skycodeoy\/","https:\/\/www.finder.fi\/IT-konsultointi+IT-palvelut\/Skycode+Oy\/Vaasa\/yhteystiedot\/1934882"]},{"@type":"Person","@id":"https:\/\/skyplanner.ai\/it\/#\/schema\/person\/d90eac23cfbf5af3a2c4a38ff10376b5","name":"Jussi M\u00e4ntyl\u00e4","image":{"@type":"ImageObject","inLanguage":"it-IT","@id":"https:\/\/secure.gravatar.com\/avatar\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g","url":"https:\/\/secure.gravatar.com\/avatar\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g","contentUrl":"https:\/\/secure.gravatar.com\/avatar\/d5cfcd5c06352082aff699784151984268501dafe5084791a9f280d4e3ec500f?s=96&d=mm&r=g","caption":"Jussi M\u00e4ntyl\u00e4"}}]}},"uagb_featured_image_src":{"full":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png",1672,941,false],"thumbnail":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-150x150.png",150,150,true],"medium":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-300x169.png",300,169,true],"medium_large":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-768x432.png",768,432,true],"large":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-1024x576.png",1024,576,true],"1536x1536":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-1536x864.png",1536,864,true],"2048x2048":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero.png",1672,941,false],"betterdocs-category-thumb":["https:\/\/skyplanner.ai\/wp-content\/uploads\/2026\/10\/changeover-matrix-hero-360x203.png",360,203,true]},"uagb_author_info":{"display_name":"Jussi M\u00e4ntyl\u00e4","author_link":"https:\/\/skyplanner.ai\/it\/author\/jussi\/"},"uagb_comment_info":0,"uagb_excerpt":"Matrice dei tempi di setup: come creare e leggere i dati Home &raquo; Risorse &raquo; Matrice dei tempi di setup: come creare e leggere i dati Una matrice dei tempi di setup \u00e8 una tabella che indica quanto tempo serve a una macchina per passare da un prodotto o da un assetto di attrezzaggio a&hellip;","_links":{"self":[{"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/posts\/100613","targetHints":{"allow":["GET"]}}],"collection":[{"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/posts"}],"about":[{"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/types\/post"}],"author":[{"embeddable":true,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/users\/3"}],"replies":[{"embeddable":true,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/comments?post=100613"}],"version-history":[{"count":1,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/posts\/100613\/revisions"}],"predecessor-version":[{"id":100979,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/posts\/100613\/revisions\/100979"}],"wp:featuredmedia":[{"embeddable":true,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/media\/100639"}],"wp:attachment":[{"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/media?parent=100613"}],"wp:term":[{"taxonomy":"category","embeddable":true,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/categories?post=100613"},{"taxonomy":"post_tag","embeddable":true,"href":"https:\/\/skyplanner.ai\/it\/wp-json\/wp\/v2\/tags?post=100613"}],"curies":[{"name":"wp","href":"https:\/\/api.w.org\/{rel}","templated":true}]}}